Import lead times are the quietest cause of a missed opening. The specified stone, the specified veneer, the specified metal finish — any one of them can run past the date.
We run a physical sample match against regional suppliers, then put the samples in front of the maison's design team. A substitute agreed on a photograph gets rejected on site; one agreed on a sample does not.
For genuinely long-lead items we pre-order against a provisional sum rather than waiting for the main contract. The cost of carrying that risk is far below the cost of opening late.
The industry tends to label us project manager or architectural consultant. Neither describes what actually happens between a maison's concept and an…
Read articleMost fit-out failures are visible at inception if someone is looking. Here is the register we build before a single drawing is issued.
Read articleSKP, IFS, Plaza 66 and Harbour City each run their own design committee. Getting approved first cycle is a preparation problem, not a design problem.
Read articleSend us the location, the opening date and the house-style pack. We'll come back with the risks we can already see, and how we would handle each one.